Monday, November 2, 2015
The Rev. Dennis H. Holtschneider, C.M. announced to the School of Music faculty and staff that the Board of Trustees approved the plans to move forward with the construction of the new School of Music facilities.

Mid-January, 2016
Demolition of McGaw will begin. This process will take six to eight weeks to complete.

March 2016
Excavation and foundation work begins, including the drilling of the 60+ deep caissons required for the structure.

Spring 2018